The smart pump retrofit advantage

12 Mar,2024

3.png

A smart pump retrofit secures flare knockout pump reliability.

To ensure the profitability of offshore oil and gas extraction, operators require equipment to perform reliably throughout long periods between maintenance intervals. When a Malaysia-based international oil company (IOC) was experiencing short mean time between failures (MTBF) for its liquified petroleum flare knockout vessel pumps on an offshore platform, the business approached Sulzer for a pump retrofit to safeguard uptime.

Flare knockout pumps are an essential component of offshore platforms. Gas or liquid from the process stream that cannot be recovered or recycled requires a release to avoid pressure build-up, so the flare system safely vents these. The excess is transported via a pump to a flare knockout vessel before combustion. A critical safety element, any pump failure in the flare system results in a total platform shutdown, stopping extraction and halting productivity.

It was exactly these failures the operator was experiencing at its platform operating offshore in east Malaysia. The two double casing diffuser vertically suspended pumps had operated reliably for several years, until a change in process caused abrasive sand to be drawn into them. Operating with a flow rate of 32m3/hr at a head of 163.9m, the pumps had a short MTBF, with failures typically occurring every 12-18 months. Excessive vibrations during running were causing the pumps to trip, with the resulting low performance not meeting the platform’s demand. In the worst-case scenario, a double pump failure would result in a complete shutdown of operations, costing the operator millions of dollars.

The operator approached Sulzer for a solution due to its reputation as a pump OEM and service provider to the oil and gas industry. After a tour of Sulzer’s Singapore service centre and a presentation on its extensive pump retrofit capabilities, the IOC selected the company to complete the work. Sulzer in Belgium was also ready to assist, ensuring that the two international teams collaborated well and effectively saw the project through to completion.

A retrofit was selected over supplying new units due to the time advantages, as Sulzer could guarantee a retrofit lead time of 26 weeks. This included manufacturing retrofit parts, carrying out modifications and conducting a performance assurance test at the Singapore service centre. Pump downtime was minimised, with the firm completing each pump retrofit individually to keep operations running. It was also possible to carry out all modifications within the existing pump footprint, ensuring easy reinstallation into the surrounding infrastructure and preserving available space on the platform.

Toughening up

Upon receiving the pump at the service centre, Sulzer dismantled it and carried out a thorough inspection. It was quite clear that the mechanism had experienced excessive wear. First, there were signs of erosion on the impellers and diffuser bowls, as well as running marks and wear on bushings, shaft sleeves and wear rings. Moving further along, blistering and running marks were found on the mechanical seals and O-ring locations, with marks on the seal’s drive collar too. During previous maintenance work, the bearings had been installed incorrectly. With access to the OEM drawings, the company could ensure the correct orientation. Finally, skidding marks were also discovered on the bearing seating area.

To combat the wear on the impellers, diffusor bowls, sleeves and wear rings, the team applied an exceptionally durable tungsten carbide coating to these components using a high velocity oxygen fuel (HVOF) thermal spray process so they could resist the debilitating effects of the abrasive process liquid. Each impeller was individually balanced, then added to the shaft until the whole assembly was correctly assembled. To solve the worn bushings, the PEEK design was upgraded to ceramic to further reduce wear. Seals were reconditioned to OEM standard and the bearing seating area was repaired. Each pump motor was refurbished in-house too as part of the turnkey project. The pumps were all tested, delivered, installed and commissioned in-line with the proposed maintenance plan.

The high-performance coatings greatly extended MTBF for the pumps, helping to secure platform uptime, productivity and profitability. Long-term, this increased durability will reduce maintenance requirements and provide operational cost savings - adding value to operations.


Contact us

Tel: 0731-84033856
Contact person: Manager Tan
Phone: 13207310455
Email: megemao@megebearing.com megetan@megebearing.com
Add: Maotang Industrial Park, Ansha town, Changsha City, Hunan Province

Follow us

手机端Mobile site

微信端WeChat

Copyright © 2018 - Changsha Mege Bearing Co., Ltd. - TECHNICAL SUPPORT: BEARING.CN
Send Inquiry